BUILDING PROCESS
| Step |
Time Frame |
Who Controls
Speed? |
|
Design
Selection |
Varies |
Homeowner |
|
Credit Approval |
1-2 weeks |
The lender or broker |
|
Final
Stamped Plans |
2-4
weeks |
MH
Imperial |
|
Site Survey/Plot Plan, etc. |
Simultaneous |
MH
Imperial |
|
Building Permit |
1 day-3 months |
Local Municipality |
|
Order
House |
9-14 weeks |
Manufacture |
|
Site
Preparation |
Simultaneous |
MH
Imperial/Mother Nature |
|
Delivery/Set and Seal |
2-4 days |
MH
Imperial |
|
Plumbing/Heating/Elect |
6-8 weeks |
MH
Imperial |
|
Finish Home |
Simultaneous |
MH
Imperial |
|
Build Decks/Garages, etc. |
Simultaneous |
MH
Imperial |
All Completed
Once you choose your design and your
builder, you can move into your dream house
within 6 months. The length of the
construction process will vary depending on
weather and site conditions. Whether it
takes 3 months or 6 months to build, we
guarantee that your home will be constructed
in a professional and workman-like manner.
We take pride in our work so that you can
enjoy your home for many years. We are
extremely meticulous, and we love to exceed
expectations.
CLICK
HERE to view/print our Sample
Construction Schedule |


 |